Tel +39 0421.760038     Fax +39 0421.760441     Mail : info@faidsrl.it

Projects carried out

Work in progress - ACTV Pontoons maintenance (Venice)

Activities for pontoons maintenance in Venice and at our factory (ACTV customer).

Application of ACTV certified cycle suitable for marine environments.
An anti-skid system with epoxy resins was applied to the roof deck.

Alborelo dam maintenance (Bolzano)

Concrete restoration and painting of the dam gates
(customer Alperia Greenpower srl).

Work on a railway bridge - Chioggia (VE)

Maintenance work on a railway bridge located in the municipality of Chioggia.

Hydro-sandblasting at a pressure of 400bar with quartz sand.
ST2 mechanical and / or manual cleaning.
Airless and / or roller brush application of epoxy and acrylic products.

Treatment of steel structures

Treatments of steel structures at the BOLOGNA FAIR:
- 400Bar water wash,
- Manual / mechanical preparation ST2,
- Application of Surface Tolerant,
- Application of polyurethane finish.

Maxi Tank - Portogruaro (VE)

Work carried out on Maxi Tank (mc 40) at our factory.
First coat application of epoxy phenolic.
Second coat application of epoxy phenolic.

Loaded and ready for departure to the installation site.

Waterproofing - Gorizia

Waterproofing activities for the roofing of the "Fiera di Gorizia" buildings

Tanks- Portogruaro (VE)

Maxi Tanks
Sandblasting and metallization wire Al 99.9
and finishing processes at our factory.

Barchessa - Torre di Mosto (VE)

Beams:
Low pressure sandblasting with fine abrasive
Woodworm and impregnating treatment

Stone walls:
Low pressure sandblasting with fine abrasive
Water repellent treatment for natural stones

Al Bayt Stadium

Structure for stadium Al-Bayt who will be the site of one of the two semi-finals of the World Cup 2022 in Qatar.

Ponte canale sul Colvera

Maniago - Risanamento del ponte canale sul Colvera

Work carried out in Congo

Applied cycle: PAINT SYSTEM 04
sandblasting Sa3;
Application of primer;
Application of epoxy intumescent;
polyurethane finish Application: DFT 3,5mm / 6,6mm

BRIDGE ON THE BOSPHORUS - Istanbul

CYCLE APPLIED:
inner surfaces
Sandblasting Sa 3 with garnet;
TSA Zn 99,9
the sealer application

exterior surfaces:
cycle in accordance with ISO 12944 FOR ENVIRONMENT C5 MH
Sandblasting Sa 2½;
Application of Zinc with epoxy, for 60μ;
epoxy intermediate application to 200μ;
Application of polyurethane, for 60μ

Belgium

Cycles Applied: CS/AFC/TS/001
Sandblasting Sa 3;
TSA Al 99,5% grado 1100 DFT 250µ ÷ 500µ

Norway

Cycles Applied: CS/AFC/TS/001 REV.03-04
Sandblasting Sa 3;
TSA Al 99,5% DFT 200µ

Villa & Bonaldi Chartek

Applied cycle

  • sandblasting Sa 2½;
  • Zincante epossidico
  • Chartek fireproofing
  • Polyurethane finish

CORDIOLI & C. SpA Railway Bridge – Bordeaux (Fr)

Cycle applied

  • Sandblasting Sa 3
  • Metallization Zn/Al 85/15
  • Sealer epoxy
  • Polyurethane finish

METALLURGICA MEDOLAGO

Ciclo Applicato

  • Sandblasting Sa 2½;
  • Inorganic zinc
  • Silicone finish

  • Sandblasting Sa 2½;
  • Zinc epoxy;
  • Chartek Fireproofing;
  • Polyurethane finish

Astaldi Spa - Hangar building c/o Air force base of Amendola (FG)

Cycle Applied : hot galvanized structures

  • Epoxy primer
  • intumescent water paint
  • polyurethane finish

Pont Schuman – Lyon (FR)

Client: Grand Lyon
Cycle applied ACQPA C4ZNV:

  • Blasting Sa 3
  • TSA Zn / Al 85/15, for a thickness of 120μ;
  • Sealer, for a thickness of 30μ
  • Intermediate epoxy, for a thickness of 70μ
  • polyurethane finish, with a thickness of 50μ.

Brasilia Stadium

Client: Farem SpA
Cycle applied:

  • Blasting Sa 3
  • Metallization Zn / Al 85/15 to a thickness of 120/1000μ;
  • Sealer for a thickness of 30μ
  • Intermediate epoxy to a thickness of 100μ
  • polyurethane finish to a thickness of 60μ.

Restoration work of art U.S. Embassy in Rome "Sabot"

Sculptor: Alexander Calder
Cycle applied:

  • Blasting Sa 3
  • Metallization Zn / Al 85/15 to a thickness of 120μ;
  • Epoxy Sealer to a thickness of 30μ
  • Topcoat.

Redevelopment district of Milan "City Life"

Architect: Zaha Hadid
Cycle applied:

  • blasting to Sa 2 ½
  • Epoxy Primer
  • Polyurea coating with a thickness of 2mm
  • polyurethane finish Florurata.

Calatrava Bridge - Venice

Architect: Santiago Calatrava
Cycle applied:

  • Blasting Sa 3;
  • Metallization Zn / Al 85/15 to 120μ;
  • Sealer for a thickness of 30/40μ;
  • Intermediate for a thickness of 150μ;
  • polyurethane finish to a thickness of 50μ.

New Convention Center Roma EUR "Nuvola"

Architect: Massimiliano Fuksas
Cycles Applied

  • Sandblasting Sa 2½;
  • Zinc epoxy to a thickness of 60µ;
  • Intermediate for a thickness of 120µ;
  • Polyurethane finish for 50µ.

  • Sandblasting Sa 2½;
  • Epoxy primer for 60µ;
  • Intumescent R60’;
  • Polyurethane finish to a thickness of 50µ


Self-leveling cement-resin application on the pavement of suspended walkways.

West Franklin Project

Client: Rosetti SpA
Cycle applied:

  • Blasting Sa 3
  • TSA At a thickness of 350μ 99.5
  • Sealer silicone to a thickness of 30μ

Intesa San Paolo Tower - Turin

Architect: Renzo Piano
Cycles applied

  • blasting to Sa 2 ½
  • Zinc epoxy to a thickness of 60μ
  • Intermediate
  • to a thickness of 180μ
  • finish to a thickness of 50μ

  • Blasting Sa 3;
  • Al Metallization to 200μ
  • Sealer for a thickness of 30μ
  • Intermediate to a thickness of 120μ
  • Polyurethane finish to a thickness of 50μ.

Consortium for cleaning

Cycle applied:

  • Pressure washing to 400 bar.
  • Reconstruction of damaged areas.
  • Cementitious waterproofing coating for crystallization.

Poliurea

Cycle applied:

  • Peening.
  • Application bottom wet epoxy.
  • Application epoxy primer cooperative.
  • Application pure polyurea, 2 mm thick.
  • Application flexible polyurethane finish to 60 microns.

Doppelmayr

Cycle applied on hot dipped galvanized surfaces.

  • Light Sand
  • Application of epoxy primer 40 micron thickness.
  • Application of polyacrylic finish for a thickness of 60 microns.

Alcoa

Cycle applied

  • Dry high pressure 1500 bar.
  • Application of high build epoxy coating 500 microns.

MOSE - Venice

Client: Consorzio Venezia Nuova
Cycle applied:

  • blasting to Sa 2 ½
  • Primer for a thickness of 50μ
  • epoxy reinforced with glass flakes, for a thickness of 500μ
  • epoxy reinforced with glass flakes, for a thickness of 500μ.

AUTOVIE VENETE - Ponte Silea

Cement cycle

  • Concrete protection systed
  • High pressure water cleaning;
  • Holas and cleaning repairs using apoxy mortar
  • Acrylic primer application
  • Top-coat application;
Steel protection system
  • Abrasive blast cleaning to Sa 2½
  • Apoxy zinc application up to 60µ Dry film thickness;
  • Apoxy intermediate application 80µ Dry film thickness
  • Polyacrylic finish application up to 50µ Dry film thickness.

RIZZANI DE ECCHER S.p.A. - Cable-stayed bridge

cycle applied

  • High prassure water cleaning;
  • Holas and craking repair;
  • Epoxy primer application;
  • Elastomeric coating application